Nigeria’s '$1.3bn Zungeru Power Project to Be Commissioned

Informações:

Synopsis

The Contractor handling Zungeru Hydroelectric Power Project, Sino Hydro, has assured that the $1.3 billion 700 Mega Watts electricity project will be commissioned in four phases in 2022. A statement by the company's Deputy Project Manager, Li Xiao Ming, stated that the first turbine which will generate 175 Mega Watts will be commissioned in the first quarter. He says the second turbine which will also generate 175 Mega Watts is expected to be commissioned second quarter while the third turbine is expected to be commissioned in the third quarter. He says the fourth turbine would be commissioned in December 2022.